Good morning, James 👋
Riverside Plaza Tower · Thursday, Feb 26, 2026
Overall Progress
68%
↑ 4% this week
Budget Used
$4.2M
of $6.7M · 63%
Workers On Site
142
↑ 18 vs yesterday
Days Remaining
84
Completion: May 20
62°F
Clear skies · Good working conditions
📍 Riverside Plaza Tower · Downtown Site
UPDATED
7:02 AM
8 mph
Wind
44%
Humidity
UV 4
UV Index
THU
64°
48°
FRI
58°
45°
SAT
52°
43°
SUN
55°
41°
MON
61°
46°
Recent ActivityView all
📋
RFI #047 — Structural beam spec clarification
✅
Inspection passed — Level 12 MEP rough-in
⚠️
Safety incident reported — Near miss, Level 8
📦
Submittal approved — Window glazing system
💰
Change order #012 submitted — $48,500
Schedule SnapshotFull →
Foundation
Structural Steel
MEP Rough-In
Exterior Skin
Interior Framing
Finishes
All Projects
4 active · 2 completed
Riverside Plaza Tower
Downtown · High-rise commercial
Progress68%
💰 $6.7M👥 142📅 May 20
Oakwood Medical Center
Westside · Healthcare
Progress42%
💰 $12.1M👥 89📅 Nov 15
Harbor Bridge Retrofit
Eastport · Infrastructure
Progress31%
💰 $3.4M👥 34📅 TBD
Sunridge Residential Ph.2
North Hills · Multifamily
Progress88%
💰 $8.8M👥 67📅 Mar 10
Drawings
312 sheets · Rev D current
| Sheet # | Title | Discipline | Rev | Date | Status | Action |
|---|---|---|---|---|---|---|
| A1.01 | Site Plan | Arch | D | Feb 18 | Current | |
| A2.14 | Floor Plan - Level 8 | Arch | D | Feb 18 | Current | |
| S3.07 | Typical Beam-Column Connection | Struct | C | Jan 30 | Superseded | |
| M4.02 | Mechanical - Level 5-10 Overview | MEP | B | Jan 15 | Current | |
| E1.10 | Electrical One-Line Diagram | MEP | A | Dec 8 | In Review |
Project Specifications
Riverside Plaza Tower · 48 sections · CSI MasterFormat
Schedule
Master schedule · 46 active tasks
Complete
84
In Progress
46
Behind
8
Not Started
33
Gantt View — Week of Feb 24
Mon 24Tue 25Wed 26Thu 27Fri 28Sat 1Sun 2
Formwork L15
Steel Erection L15
MEP Rough-In L8
Curtainwall L10-12
Drywall Framing L5
Elevator Install Shaft A
Plumbing Rough-In L9
RFIs
7 open · 2 urgent · Avg response 3.2 days
Open
7
Answered
40
Closed
31
Overdue
2
| # | Subject | Ball In Court | Submitted | Due | Priority | Status | |
|---|---|---|---|---|---|---|---|
| ⏳ Connecting to database… | |||||||
Submittals
14 open · 28 approved
| # | Title | Spec Section | Submitted | Due | Status | |
|---|---|---|---|---|---|---|
| ⏳ Connecting to database… | ||||||
Deficiency List
12 open · 5 critical · 47 closed
Critical
5
High
4
Normal
3
Closed
47
| # | Description | Location | Trade | Assigned To | Due | Priority | Status | |
|---|---|---|---|---|---|---|---|---|
| ⏳ Connecting to database… | ||||||||
Photos
2,847 photos · 12 albums
📅 Today — February 26, 2026Today
Albums
Documents
All project documents
| Name | Type | Size | Uploaded By | Date | Action |
|---|---|---|---|---|---|
| 📄 Project Budget Report Q1 2026.pdf | 2.4 MB | J. Davis | Feb 20 | ||
| 📊 Budget Tracker 2026.xlsx | Excel | 1.1 MB | J. Davis | Feb 18 | |
| 📄 Concrete Mix Design Report.pdf | 840 KB | P. Williams | Feb 14 | ||
| 📊 Master Schedule Tracker.xlsx | Excel | 3.2 MB | J. Davis | Feb 12 | |
| 📄 Site Safety Plan Rev 3.pdf | 5.6 MB | M. Torres | Feb 5 |
Budget
$6.7M total contract
Original Contract
$6.70M
Approved Changes
+$248K
Revised Contract
$6.95M
Invoiced to Date
$4.21M
| Code | Description | Budget | Changes | Revised | To Date | % Used | Forecast |
|---|---|---|---|---|---|---|---|
| 03-00 | Concrete | $1,240,000 | +$18,000 | $1,258,000 | $1,190,000 | 94% | $1,270,000 |
| 05-00 | Structural Steel | $890,000 | +$48,500 | $938,500 | $760,000 | 81% | $920,000 |
| 15-00 | Mechanical | $980,000 | +$12,000 | $992,000 | $340,000 | 34% | $985,000 |
Daily Logs
Riverside Plaza Tower
📅 Thursday, February 26, 2026Today
Weather
☀️ 62°F
Clear · Wind 8 mph
Manpower
142
Workers on site · 12 crews
Deliveries
8
Scheduled today
Log History
| Date | Weather | Workers | Key Activity | Issues | Logged By |
|---|---|---|---|---|---|
| ⏳ Connecting to database… | |||||
Inspections
3 scheduled today
Passed
89
Failed
4
Pending
3
Pass Rate
96%
| Date | Type | Location | Inspector | Result | |
|---|---|---|---|---|---|
| ⏳ Connecting to database… | |||||
Incidents
Safety & Incident Register
Days Without Incident
12
Near Misses YTD
3
OSHA Recordables
0
Open Investigations
1
| Date | Type | Location | Description | Severity | Reported By | Status | |
|---|---|---|---|---|---|---|---|
| ⏳ Loading… | |||||||
Invoices
Pay applications & billing
| Pay App # | Period | Amount | Retention | Net Due | Status | |
|---|---|---|---|---|---|---|
| #008 | Feb 1–28, 2026 | $480,000 | $24,000 | $456,000 | Submitted | |
| #007 | Jan 1–31, 2026 | $510,000 | $25,500 | $484,500 | Approved | |
| #006 | Dec 1–31, 2025 | $490,000 | $24,500 | $465,500 | Paid |
Contracts
Prime contract & subcontracts
| Company | Scope | Contract Value | Change Orders | Revised Value | Status | |
|---|---|---|---|---|---|---|
| Crestline Steel | Structural steel supply & erect | $938,500 | +$48,500 | $987,000 | Active | |
| Alpha MEP | Mechanical, electrical, plumbing | $1,740,000 | $12,000 | $1,752,000 | Active |
Change Orders
5 pending · $412,000 in review · $248,000 approved
Pending
5
Approved
12
Value Pending
$412K
Value Approved
$248K
⏳ Pending / In Review5 items
⏳ Loading…
✅ Recently Approved12 total
| # | Description | Category | Amount | Days | Approved | |
|---|---|---|---|---|---|---|
| ⏳ Loading… | ||||||
Time & Materials
T&M Sheets — Riverside Plaza Tower · 8 open tickets
⏳ Loading T&M sheets…
Pay Application #08
Period: Feb 1 – Feb 28, 2026 · Riverside Plaza Tower
Original Contract
$6,780,000
Net CO Amount
+$217,000
Revised Contract
$6,997,000
Net Due This Draw
$0
📋 Schedule of Values
Drag sliders to update % complete · retainage 10%
| Item | Description | Scheduled Value | % Complete | This Period | Retainage | Net Earned |
|---|---|---|---|---|---|---|
| TOTAL | $6,997,000 | — | — | — | — | |
Previous Pay Apps
| # | Period | Amount | Status |
|---|---|---|---|
| #07 | Jan 1–31 | $482,000 | Paid |
| #06 | Dec 1–31 | $394,000 | Paid |
| #05 | Nov 1–30 | $411,000 | Paid |
| #04 | Oct 1–31 | $298,000 | Paid |
Cumulative Progress
Earned to date vs contract value
$0$0 earned$6,997,000
Meeting Minutes
Weekly coordination · Riverside Plaza Tower
Meetings This Month
8
Open Action Items
14
Overdue Actions
3
⚡ Open Action Items14 open
⬜
James D — Confirm crane lift schedule with structural for L16 pour
Due Mar 5 ⚠
⬜
Amir S — Issue revised curtainwall anchor detail drawing
Due Mar 7 ⚠
⬜
Kyle J — Submit T&M ticket for rock excavation Grid G-7
Due Mar 10
⬜
Maria T — Arrange re-inspection for fire stopping L11
Due Mar 12
⬜
Rachel C — Provide seismic calcs for revised core wall section
Due Mar 15
📋 Meeting Archive
Weekly Coordination — Mar 3, 2026
Weekly Coordination — Feb 24, 2026
OAC Meeting — Feb 20, 2026
Safety Review — Feb 18, 2026
Labour Histogram
Planned vs actual headcount by trade — week of Mar 3, 2026
On Site Today
47
+3 vs plan
Peak This Week
62
Wednesday
Labour Hours MTD
3,840
↑ 94% of plan
Trades On Site
8
Daily Headcount — This Week
Planned
Actual
All Trades
Concrete
Steel
MEP
Formwork
Finishing
Trade Breakdown — Today
| Trade | Planned | Actual | Variance | Foreman | Area |
|---|
Toolbox Talks
Daily safety briefings · 100% coverage required
This Month
22
All crews covered ✓
Total Attendees MTD
486
Avg Duration
12min
Topics This Month
8
Recent Toolbox Talks
03
Mar
Working at Heights — Harness Inspection Procedure
Kyle JDan MS. Kowalski
A. ReyesB. Park+19 more
28
Feb
Concrete Pour Safety — Hot Weather Protocols
Concrete Crew AConcrete Crew B+10 more
27
Feb
Crane Exclusion Zones — Revised Lift Plan L16
All site crewSubcontractors
25
Feb
PPE Requirements — Eye & Face Protection Update
MEP CrewFinishers+14 more
Material Deliveries
Incoming materials — Riverside Plaza Tower
Expected Today
3
Received This Week
11
Short / Deficient
2
Pending QA Check
4
Recent Deliveries
Structural Steel — W-Sections L16 Columns
Curtainwall Panels — East Facade L8–L12
Waterproofing Membrane — Podium Level
Ready-Mix Concrete — L15 Slab Pour
MEP Ductwork — L13–L15 Mechanical
Inspection Checklists
Reusable templates · fill on site with pass/fail/N/A
📋 Templates
Concrete Pour Checklist
18 ✓
MEP Rough-In Inspection
24 ✓
Facade Closeout
31 ✓
Fire Protection Inspection
14 ✓
Level Handover — Deficiency Clearance
42 ✓
📊 Recent Runs
| Template | Level | Date | Pass | Fail | Result |
|---|---|---|---|---|---|
| Concrete Pour | L15 | Feb 27 | 18 | 0 | Passed |
| MEP Rough-In | L12 | Feb 25 | 22 | 2 | With Defects |
| Facade Closeout | L6 | Mar 1 | 28 | 3 | With Defects |
| Fire Protection | L6 | Feb 22 | 11 | 3 | Failed |
| Concrete Pour | L14 | Feb 20 | 18 | 0 | Passed |
Directory
Project team · 38 contacts
| Name | Company | Role | Phone | Status |
|---|---|---|---|---|
| ⏳ Connecting to database… | ||||
Roles & Permissions
Manage access control for your project team
Punch List
12 open · 3 in progress · 2 pending inspection
🔴 Open
6
PL-001
Touch-up paint — L4 Corridor
PL-002
Replace cracked tile — L2 Lobby
PL-003
HVAC grille misaligned — L6 Office
PL-004
Door closer adjustment — L3 Stairwell
PL-005
Sealant gap at window frame — L8 W-Face
PL-006
Light fixture not level — L5 Meeting Rm
🔵 In Progress
3
PL-007
Waterproofing at base of parapet — Roof
PL-008
Acoustic ceiling tile replacement — L9
PL-009
Paint touch-up stairwell handrail — L7
🟡 Pending Inspection
2
PL-010
Fire stopping re-penetration — L11
PL-011
Expansion joint cover installation — L3
✅ Closed
1
PL-012
Missing cover plate on electrical panel — B1
📷
My Profile
Manage your account, preferences, and notifications
JD
✏️
James Davis
Project Manager
Meridian Construction
👤 Personal Information
🔒 Security
🔔 Notification Preferences
RFI Responses
When RFIs assigned to you get answered
Deficiencies
New deficiencies raised on your tasks
Messages
Direct messages and @mentions
Submittals
Status changes on submittals
Budget Alerts
When line items exceed threshold
Daily Log Reminders
Reminder to submit daily report at 4pm
Push Toasts
In-app notifications when active
Schedule Milestones
Upcoming schedule deadlines
📊 Recent Activity
Submitted RFI #047 — Structural beam spec
Approved Submittal #031 — Steel connections
Logged daily report — L15 concrete pour
Sent message in #general — curtainwall update
Raised deficiency DEF-089 — waterproofing
🎮 Demo Mode
Explore with sample data
☁️ Account
Not connected — running in demo mode
Billing & Plan
Loading your plan…
Current Plan
—
—
—
per month
📊 Usage This Month
Projects
—
Team Members
—
Documents Created
—